Paynters engaged Sunshine Coast Civil to deliver the site works package for the new Boyne Tannum Aquatic Centre, a Gladstone Regional Council facility at Boyne Island. We are moving 25,791 m³ of earth in two stages, excavating the pool formation in rock, and building the stormwater, pavements and concrete works across both the centre site and the external roads on Wyndham Avenue.
Scope of works
25,791 m³
Cut to fill, two stages
26,172 m²
Asphalt
568 m
Kerb, various types
1,380 m²
Concrete works
Stormwater and water quality
280 m of stormwater, a 2300 pollution trap, a DM3300 storm filter and an urban pond.
Internal and external works
Pool formation excavated in rock, with pavements, kerb and drainage also built in the external roads on Wyndham Avenue.
Project team: Simon Cornwell · Chris Hackett