Sunshine Coast Civil delivered the civil works for a new 6-lot acreage subdivision on Gardners Lane, Maleny, in the Sunshine Coast hinterland.
Scope of works
2,500 m³
Cut to fill
1,000 m²
Road
1,600 m²
Swales
Our scope covered bulk earthworks, roadworks, drainage with swales and multiple culvert crossings, rock scour protection, and electrical and NBN consumer conduits for each lot.
Plenty of wet weather made for a challenging build, but the team kept the environmental and sediment controls working and delivered the job on time and on budget.