For Sunstruct, Sunshine Coast Civil delivered the bulk earthworks for a 35-townhouse development on Stevens Street, Yandina.
Scope of works
1,700 m³
Cut to fill
2,300 m³
Imported fill
3,400 m²
Building pads
355 m
Retaining wall drainage
1
Bioretention basin
We stripped the site, cut, filled and compacted the building pads and driveway, and placed drainage and backfill behind the retaining walls. We also built a bioretention basin and ran erosion control with a high-efficiency sediment basin. All site traffic used Buckle Street to keep disruption to neighbours down.